MRP (material requirements planning) is a method, usually built into an ERP, that works out which materials a manufacturer needs, how many and by when, based on what it plans to build.
ERP · Reviewed by Ray Rasouli
Ask about MRP
Plain answers, with your setup in mind.
Ask anything about MRP. For example, how it works in your current tools.
A scripted guide for now. It does not store what you type.
MRP starts with what you plan to make, then breaks each product down using its bill of materials. It subtracts what is already in stock or on order and tells you what to buy or make, and when, to finish on time.
Say a furniture maker plans 200 chairs for next month. Each chair needs four legs, one seat and a set of screws. MRP checks stock, sees 300 legs on hand, and suggests a purchase order for the other 500 with enough lead time to arrive before assembly.
MRP is only as good as its inputs. Wrong lead times or bills of materials give confident but wrong suggestions.
The usual flow, step by step.
In practice
Bills of materials are out of date.
If engineering changes a part but the BOM is not updated, MRP orders the wrong components.
Lead times in the system are guesses.
Suppliers that take longer than the recorded lead time cause late materials, even when MRP ran correctly.
Planners ignore the suggestions.
After a few bad runs, staff stop trusting MRP and go back to ordering by feel.
Stock records are inaccurate.
MRP assumes the inventory counts are right. If they are not, it overbuys some items and runs short on others.
MRP is the planning piece that calculates material needs. ERP is the wider system that also covers finance, sales, purchasing and more, and usually includes MRP as a module.
MRP II (manufacturing resource planning) extends MRP to also plan machine capacity, labour and costs, not just materials.